Water and Sewer for Torrens Subdivision
The requirements for those INSIDE the Sydney Water distribution and OUTSIDE are DIFFERENT.
- Within Sydney : Sydney Water is likely your Water Authority.
- Outside Sydney : please refer to the Outside of Sydney Water section of this webpage.
- To confirm, please visit the Sydney Water’s Area of Operation Map.
INSIDE Sydney Water Distribution Network
You need a S73 Compliance Certificate (“Torrens Subdivision”). Submit the following to your Water Servicing Coordinator:
1
CDC approval for Subdivision that we have issued you
- This document will be named “CDC#####_01.pdf.”
- You need to use the same WSC as you used for the building.
PPN number from your registered surveyor
3
Draft Subdivision Plan
Once submitted and fees are paid, it is generally processed in 2-3 weeks. Refer to the example for a Section 73 Certificate.


OUTSIDE Sydney Water Distribution Network
You need a Compliance Certificate from the Local Sewer and Water Authority (the Local Council).
1
Fill out application form on the council’s website.
2
Attach CDC approval for subdivision that we have issued you with your application
- This document will be named “CDC#####_01.pdf.”
Once submitted and fees are paid, it is generally processed in 2-3 weeks. Refer to the example for S307 and S68 approvals.