Water and Sewer for Torrens Subdivision


You need a SEPERATE Water and Sewer approval to the one you received for the building. You will have 2 x S73's at the end of the project.

The requirements for those INSIDE the Sydney Water distribution and OUTSIDE are DIFFERENT.



- Within Sydney : Sydney Water is likely your Water Authority.


- Outside Sydney : please refer to the Outside of Sydney Water section of this webpage.


- To confirm, please visit the Sydney Water’s Area of Operation Map.

INSIDE Sydney Water Distribution Network


You need a S73 Compliance Certificate (“Torrens Subdivision”). Submit the following to your Water Servicing Coordinator:


1

CDC approval for Subdivision that we have issued you


  • This document will be named “CDC#####_01.pdf.”
  • You need to use the same WSC as you used for the building.
2

PPN number from your registered surveyor


3

Draft Subdivision Plan



Once submitted and fees are paid, it is generally processed in 2-3 weeks. Refer to the example for a Section 73 Certificate.






This is NOT a Section 73 Certificate for Subdivision



OUTSIDE Sydney Water Distribution Network


You need a Compliance Certificate from the Local Sewer and Water Authority (the Local Council).


1

Fill out application form on the council’s website.


2

Attach CDC approval for subdivision that we have issued you with your application


  • This document will be named “CDC#####_01.pdf.”

Once submitted and fees are paid, it is generally processed in 2-3 weeks. Refer to the example for S307 and S68 approvals.